Staged Payment Schedule: You Only Pay for Finished Work

Your money should never run ahead of the work. Every payment is tied to a construction stage that can be seen and verified — not a calendar date, not a big advance. This is our reference schedule, following the same pattern LPPSA and the panel banks use.

Stages
7
Confirmation deposit
5%
Retention
5%

One of the questions asked most often, and answered least clearly in this industry: when does the money go out? The table below is the answer. Each stage states what must be finished and verified before a claim is made.

The example below uses a construction cost of RM450,000 to show the real amount at each stage. The final schedule and terms are set out in your contract; the contract is what binds, not this page.

Stage Verification required % Example RM450,000
1. Confirmation deposit After the contract is signed and the working drawings are finalised. This books your construction slot and starts mobilisation. Contract signed, approved plans received 5% RM22,500
2. Site work & foundations Site clearing, setting out, excavation, concrete footings and foundations completed, tested and verified by the engineer. Foundations verified, the relevant Form G signed 15% RM67,500
3. Ground-floor structure Ground-floor columns, beams and slab completed. For a two-storey house, this includes the upper floor slab. Structure verified by the engineer 20% RM90,000
4. Walls & roof Brickwork, roof frame and tiles installed. The house becomes weathertight at this stage. Roof complete, house watertight 20% RM90,000
5. M&E & plastering Electrical wiring, water piping, sewerage, and plastering of walls and ceilings. Plumbing and wiring tests passed 15% RM67,500
6. Finishes Tiles, doors, windows, kitchen cabinets, bathroom fittings, paint and external finishes. All finishes installed 20% RM90,000
7. Handover & retention Paid after a joint inspection and once the defects list is cleared. This is the retention that makes sure defects are fixed before the final payment. Defects list cleared, keys handed over 5% RM22,500
Total 100% RM450,000

How progress claims work

If you finance through LPPSA or a bank, you do not pay us directly during construction. The process:

  1. A stage of work is completed on site.
  2. An engineer or supervisor verifies the work complies with the approved plans and signs the stage certificate.
  3. We prepare the progress claim in the format the financier expects.
  4. The financier checks it, then pays us directly.
  5. You receive a record of every disbursement.

Our status as an LPPSA, CIMB and Maybank panel contractor means our claim documents already follow the format they expect. That shortens disbursement times, and it is the only practical benefit of panel status you will actually feel.

Frequently asked

Who pays — me or the financier?
If you finance through LPPSA or a bank, the financier pays us directly against verified progress claims. You do not hand over cash at each stage. If you pay in cash, you pay to the same schedule.
What happens if a stage is slow to be verified?
Work does not stop, but the claim is not paid until verification is received. That is why stage inspections need to be scheduled early, not requested on the day the claim is sent.
Can I withhold payment if I am not satisfied?
The last stage — the 5% retention — is designed exactly for that. It is paid only after a joint inspection and once the defects list is cleared. For the other stages, the engineer's or supervisor's verification is the basis of the claim, so disputes are settled at verification, not at payment.
Does a variation order change this schedule?
Yes. Changes of scope during construction are added as separate items with their own price and payment stage, agreed in writing before the work is done. We do not carry out extra work on the strength of a conversation — it protects both sides.
Why is the deposit only 5%?
Because a large deposit moves the risk onto you before any work is done. 5% covers mobilisation and the working drawings; the rest is tied to progress you can see and verify. If a contractor asks for 20% or 30% in advance, ask what you get for that money.

See the real figures for your project

The cost estimator gives the overall total; our formal quotation breaks it into the seven stages above, with the exact amount for each. Both are free.

WhatsApp Free Quotation